Sprint 2 - Integrations Retrospective
Date | Oct 6, 2020 |
---|---|
Team | ICT Integrations |
Participants | @Brad Fernandes (Unlicensed) @Jules Levin @Rakesh Thobula Ramulu @Vinay Kumar T M (Unlicensed) @Yeng Sembrano |
Background
The Sprint objectives covered key area -
Integrations
Statistics at the end of Sprint
Cumulative Flow Diagram
Retrospective
Conducted using IdeaBoardz to collaborate and gather feedback. Participants were given an opportunity to vote on the feedback for discussion.
What went well? | |
Point | Votes |
quick action from everyone in lifting blockers, responses to jira comments. Good team work | 4 |
AQ and integration partnership is still going well | 1 |
iModules discussion with Monica and narrowing down the discussion on gift batching | 1 |
higher completion rate compared to sprint 2 | 1 |
SITS integration is shaping up, creation of accounts and contacts were showcased by Vinay | 1 |
Good communications with Advancement teams (Yeng, Manpreet,etc.) and ICT (Vinay, Rakesh, etc.) on data mappings & tech desig | 1 |
What can be improved? | |
Point | Votes |
gaps between AQ, business and integrations. | 0 |
minimise adding User Stories/ Tasks to existing Sprint unless they are related | 0 |
Action items
Action Items | |
Point | Votes |
Agile Team should attend key Scrum ceremonies (Sprint Planning, Sprint Review, Sprint Retrospective) | 0 |
Engage with AQ to discuss design decisions prior to build and test by Integrations team. | 0 |