Sprint 17 [Egg roll]

Attention: Confluence is not suitable for the storage of highly confidential data. Please ensure that any data classified as Highly Protected is stored using a more secure platform.
If you have any questions, please refer to the University's data classification guide or contact ict.askcyber@sydney.edu.au

Sprint 17 [Egg roll]

Date

Jun 17, 2021

Team

TAP Product Line

Project Participants

@Brad Fernandes (Unlicensed)  @Rachel Forbes @john.humphreys @Manpreet Sidhu @Sidra Zafar @Himanshu Raikar (Unlicensed) @The Ho Trang @Yeng Sembrano @AlainGasquet@Chanel Zheng @Monica Kluegel @Divyanshu Pandey (Unlicensed) @abraham

Apologies

@apirami.kumaradevan

Background

Sprint 17 achievement are listed as -

  • Cyber Security Penetration testing completed

  • Stata and MiniTab licenses procured and Predictive modelling commenced

  • Aperture DS training commenced.

  • Updates to the Pledge reminder notice

  • Enhancements to Peoplesoft files

  • Gift in Will stage

  • Updates to Opportunity - Ask amount,

  • Community Giving Dashboards

  • Funds raised by Alumni

  • Optimise the flows for Gift processing - Raised with Salesforce

  • Gift club memberships

  • Data conversions fixes to Addresses (suburbs)

  • Receipts to be on-hold -

  • Annual receipts

  • Event registration

  • Updates to CG dashboards

Statistics at the end of Sprint

Retrospective

Conducted using IdeaBoardz to collaborate and gather feedback. Participants were given an opportunity to vote on the feedback for discussion.

What went well?

Point

Votes

We still like each other!

7

Good team communication and collaboration

3

clear goals in place

2

Technology Roadmap provides a framework of priorities for 6 months

2

Big ticket items being completed

0

In office face to face discussions about different tasks help a lot in navigating it to completion.

0

3 week sprint is a good idea

0

What can be improved?

Point

Votes

better understand what resources are available for planning

1

Focus on blocks of stories / functions to consolidate adding value per sprint (no spreading across too many elemenets)

0

Mapping dependencies / stress period for external stakeholders (e.g. ASR with appeals, EOY, etc.)

0

ensure must have items are allocated to a developer at the start of the sprint so we know what we can deliver

0

Action Items

Point

Votes

Drinks

3

 

 

 