Sprint 9 and Sprint 10 - Status
Due to the Christmas shutdown period, Sprint 7 and Sprint 9 was extended for a week, and Sprint 8 was cancelled.
Due to time constraints, there was no Sprint Review or Sprint Retrospective for these Sprints. A project Post-implementation review (PIR) will be held at a later date.
Date | Jan 26, 2021 |
---|---|
Team | Project Phoenix team/ ICT Integrations |
Project Participants | @Brad Fernandes (Unlicensed) @Jules Levin @Rakesh Thobula Ramulu @Vinay Kumar T M (Unlicensed) @Yeng Sembrano @AlainGasquet@Manpreet Sidhu @Monica Kluegel @Trevor Lindsey (Deactivated) @Sidra Zafar @Rachel Forbes @john.humphreys @Ekta Patel (Unlicensed) @The Ho Trang @apirami.kumaradevan@alexia nicholson (Unlicensed) |
Background
The project successfully went live and activated all TAP users on Jarvis on 21/01.
Sprint 9 and Sprint 10 objectives covered key areas for -
Integrations
Final data Conversion
Reporting
Opportunities
Gift Administration
Community Giving
Change Management
Statistics at the end of Sprint