Sprint 11 - Sprint Review

Attention: Confluence is not suitable for the storage of highly confidential data. Please ensure that any data classified as Highly Protected is stored using a more secure platform.
If you have any questions, please refer to the University's data classification guide or contact ict.askcyber@sydney.edu.au

Sprint 11 - Sprint Review

Date

Feb 9, 2021

Team

Project Phoenix team/ ICT Integrations

Project Participants

@Brad Fernandes (Unlicensed) @Jules Levin @Rakesh Thobula Ramulu @Vinay Kumar T M (Unlicensed) @Yeng Sembrano @AlainGasquet@Manpreet Sidhu @Monica Kluegel @Sidra Zafar @Rachel Forbes @john.humphreys @The Ho Trang @apirami.kumaradevan@alexia nicholson (Unlicensed)

Background

The project successfully went live and activated all TAP users on Jarvis on 21/01.

Sprint 11 objectives covered key areas for -

  • Integrations

  • Final data Conversion testing/ bugs

  • Gift Processing

Sprint 11 was limited to 8 business days due to Australia Day long weekend. Since the project went live on 21/01, the project team was scaled down by 2 developers (Ekta and Trevor). Additionally, the team were involved in Post-Production support to respond to enquiries and make a few break-fixes.

Despite the time above constraints, the team still closed out 91 tickets (Done + Cancelled).

Statistics at the end of Sprint

Retrospective

There was no Retrospective in lieu of a Project PIR (Post Implementation Review) conducted on 05/02. The report will be made available at a later date.

 