Background
The Sprint objectives covered key area -
Integrations
Statistics at the end of Sprint Review
Cumulative Flow Diagram
Retrospective
Conducted using IdeaBoardz to collaborate and gather feedback. Participants were given an opportunity to vote on the feedback for discussion.
What went well? | |
Point | Votes |
Daily progress report by Brad and his dashboard gives a better overall view of our progress, keeping us more informed | 3 |
Collaboration between integration team and TAP team members | 2 |
Access to AQ | 1 |
Build of SITS to Salesforce | 1 |
EzeScan to Salesforce - blocker lift | 1 |
I liked the Stand-up meeting where everybody got an opportunity to give an update | 0 |
Communications with AQ | 0 |
What can be improved? | |
Point | Votes |
Break up Jira tickets into smaller sprint size tasks | 2 |
Update Jira tickets on time | 2 |
Combine Integrations and Configurations team for all Scrum ceremonies. | 1 |
Action items
Action Items | |
Point | Votes |
Get confirmation from eZscan and Salesforce about Solution Architecture | 0 |