Sprint 5 - Integrations Retrospective

Attention: Confluence is not suitable for the storage of highly confidential data. Please ensure that any data classified as Highly Protected is stored using a more secure platform.
If you have any questions, please refer to the University's data classification guide or contact ict.askcyber@sydney.edu.au

Sprint 5 - Integrations Retrospective

Date

Nov 17, 2020

Team

ICT Integrations

Participants

@Brad Fernandes (Unlicensed) @Jules Levin @Rakesh Thobula Ramulu @Vinay Kumar T M (Unlicensed)

Background

The Sprint objectives covered key area -

  • Integrations

Statistics at the end of Sprint

Cumulative Flow Diagram

Retrospective

Conducted using IdeaBoardz to collaborate and gather feedback. Participants were given an opportunity to vote on the feedback for discussion.

What went well?

Point

Votes

Team collaboration working well.

1

Issues are detected early and remediated relatively quickly

1

SITS integration sign off

1

Recognition from the Steering Committee, expressing gratitude & admiration for project team's  high performance within tight timeframe & bgt

0

ARB Approval on Sol Design.

0

What can be improved?

Point

Votes

requirements from end user needs to be orchestrated without gaps.   Ex: Peoplesoft GL codes validation requirements exploded 3 times when discussed with gift processing team.

1

2 sprints remaining and still plenty of integration work remaining. Need to prioritise on MVP delivery.

0

Action items

Action Items

Point

Votes

 

 

 

 

 

Related content

Sprint 2 - Integrations Retrospective
Sprint 2 - Integrations Retrospective
More like this
Sprint 7 - Integrations Retrospective
Sprint 7 - Integrations Retrospective
More like this
Sprint 3 - Integrations Retrospective
Sprint 3 - Integrations Retrospective
More like this
Sprint 4 - Integrations Retrospective
Sprint 4 - Integrations Retrospective
More like this
Sprint 1 - Integrations Retrospective
Sprint 1 - Integrations Retrospective
More like this
Sprint 6 - Integrations Retrospective
Sprint 6 - Integrations Retrospective
More like this