Sprint 12 - Sprint Review/ Retrospective

Attention: Confluence is not suitable for the storage of highly confidential data. Please ensure that any data classified as Highly Protected is stored using a more secure platform.
If you have any questions, please refer to the University's data classification guide or contact ict.askcyber@sydney.edu.au

Sprint 12 - Sprint Review/ Retrospective

Date

Feb 23, 2021

Team

TAP Product Line

Project Participants

@Brad Fernandes (Unlicensed) @Jules Levin @alexia nicholson (Unlicensed) @Rachel Forbes @john.humphreys @Monica Kluegel @Manpreet Sidhu @Sidra Zafar @Himanshu Raikar (Unlicensed) @The Ho Trang @Yeng Sembrano @AlainGasquet@Chanel Zheng @apirami.kumaradevan@alexia nicholson (Unlicensed)

Background

Sprint 12 priorities were -

  1. Compliance - Receipt/ Gift Processing

  2. External stakeholders & Mass communications

  3. Internal TAP

  4. Finalise Data conversion

Sprint 12 was limited to 9 business days due to TAP planning day (17/02). Additionally, ICT integrations team worked for 6 days on the Sprint as they were re-directed to Curriculum Timetable (CT) and Workday projects.

Despite the time above constraints, the team closed out 62 tickets (Done + Cancelled).

Statistics at the end of Sprint

Retrospective

Conducted using IdeaBoardz to collaborate and gather feedback. Participants were given an opportunity to vote on the feedback for discussion.

What went well?

Point

Votes

Focus on core priorities to ensure proper gift processing / data mapping fixing

4

Collaboration team work among task assigned work well

1

Integrations are activated in Prod and number of issues identified have reduced.

0

Teams Team Teams

0

Systems knowledge and best practices shared with team members

0

What can be improved?

Point

Votes

Take into account capacity when Sprint planning

2

redistribution / planning of stories towards future sprints

1

Team collective energy needs to be re to be waning.

1

Back to parallel handling BAU and Sprint work

0

Action Items

Point

Votes

Clear workload estimation of what is possible to manage within one sprint

2

Transparency regarding priorities by sprint / identifying what success looks like

0

Have a working group to complete data conversion testing.  YS, MK, JH - Gifts, Recurring Gifts TT - Tax appeal,  MS, SZ - Opportunities, CG, PD  H -Receipting, iMods,

0

Small sprint update shared after each sprint to the TAP Phoenix teams chat

0

Build in sprint breaks to refocus and catch up - after 19th March - 4 week break?

0

Decommission planning

0

 

 