2020-11-11 Stand-up notes
Date
Nov 11, 2020
Participants
@Jules Levin
@Brad Fernandes (Unlicensed)
@Lori Stirling (Deactivated)
@Griffin Homan (Deactivated)
@apirami.kumaradevan
Standing Agenda
Progress against plan
Outstanding actions
Blockers
Focus for next week
Focus for following week
General
Discussion
Progress against plan
Data conversion - Lori and Griffin reviewing defects list. Griffin and Lauren going through open items. Griffin says between 10 and 20 outstanding issues. 5 Gift related and rest are bio related. About 20 ticket relate to last modify and update dates. Will tackle last. About 10 outstanding related to opportunities. Once that sorted will go away. More Jira tickets than issues. @Jules Levin to setup up a test review. Can test be re-assigned. Fix the outstanding ones by Friday our time. Have someone to walk through from yeng team and CSMs..
To mitigate prolonged final data conversion, @Lori Stirling (Deactivated) advised that her and Griffin will go though test cases for the list of defects during the Xmas break. prior to USYD commencing data conversion testing on 4 January.
Target Friday to close out defects. UAT commences on 23 November. Dependency for UAT is to refresh the UAT sandbox with PROD data.
Assess on Friday about refresh UAT.
How can PD do mass modify opportunity and account assignments - Load new release in December. Lori offer they would do it over the break if USYD wants to introduce the new release
Outstanding Actions
See above
Blockers
Refinement data conversion
Focus for next week
Continue Sprint 5
Data conversion testing
Focus for following week
Complete Sprint 5.
UAT data refresh
Action items
Outstanding Actions