2020-07-15 Stand-up notes
Date
Jul 15, 2020
Participants
@Jules Levin
@Brad Fernandes (Unlicensed)
@Lori Stirling (Deactivated)
@Griffin Homan (Deactivated)
@apirami.kumaradevan
Standing Agenda
Progress against plan
Outstanding actions
Blockers
Focus for next week
Focus for following week
General
Discussion
Progress against plan
Three sets of data run in for campaigns. One set has issues.
Errors preventing relationships
Had to dump gifts due to error in the gift file
Loaded pledges.
A few unusual things discovered in TMS tables
Loading campaigns.
Looking at errors such as batches out of sync. Looks like to do with daylight savings time
Will be looking at issues list
Additional 10GB of space allocated in SF org
Outstanding Actions
None
Blockers
Errors with loading conversion data
Focus for next week
Finish data conversion testing
Process workshops
Implementation sprints - @Lori Stirling (Deactivated) has done a pass through and update of the items in the Jira backlog. Lori will do another pass through and update.
Steerco meeting on 21 July. @Lori Stirling (Deactivated) to attend for first 15 min and show an overview of what has been setup in the AQ org.
@Yeng Sembranoand team to fix Advance identified defects in preparation for next Advance export
Focus for following week
Continue with process workshops
@Jules Levin to arrange datadump of Advance tables for 27 July
After Gift processing workshop determine number of Apsona licences required.
@Griffin Homan (Deactivated) Griffin to look at dependent pick lists so that set correctly in prd
Every contact had its own household which is an issue - @Lori Stirling (Deactivated) to investigate
Wait to see in prod for refinement. Want to clarify.
Action items