    Q4 priorities - Priorities by EPIC

    Priority planning for TAP Product Line (Solution Slayers) for work commencing ___ October.
    Key Stakeholders:
    Api, Laila Valterio, Alain Gasquet, Jessica Wood, Monica Kluegel, , Miranda Adams

    People to inform:
    Tina Verna, Demelza Birtchnell… (Please add people here)



    GA team time dependencies:
    Internal Audit - present to end of October
    AQ consult - aiming 16 October
    GA/ GI - assessment - Oct to November
    End of year processing - mid November - Dec shut down

    Rank

     

    EPIC

    Sizing

    Duration estimation (minimum)

    Business requirements

    Business SME required

    Impact/Dependencies

    To be included in Q4

    Status

    Rank

     

    EPIC

    Sizing

    Duration estimation (minimum)

    Business requirements

    Business SME required

    Impact/Dependencies

    To be included in Q4

    Status

     

    Sydney Student - fix mulesoft integration

    TAPSS-318

    Large (5 to 6 sprints)

    2.5 month

    Assessment + Build

     

     

     

    16 stories completed

     

    Integration fix - iModules

    TAPSS-1160

     

     

     

    Beha

    Vendor management - -raise

    Needs further assessment

    Requires confirmation

     

    Swift and swoogo

     

    Extra Large

     

    Feedback from SME (Jess):

    Swoogo- event platform - not inegratied
    Swift - invites and mass comms to drive rego, social media, campaign activity… leads to swoogo for regration

    Spent 12 months previously to integrated

    Jess and Polina

    Check Luke demo

    IF we are using Swoogo/swift - check with jess

    What are the blockers?
    Integration -
    Alumni Festival - camapign leads up
    Update your details
    lost alumni

    Q4

    N-
    based on Jess’s feedback, Swoogo is governed by a central team and is currently used by events team in TAP for event registration. There is also a wider procurement process being undertaken for an event platform.

    Without clear understanding of the final event platform for the University - Swoogo doesn’t require product teams' involvement in Q4.

    In regards to Swift, Jess advised that previously 12 months of effort was spent on integrating swift to Jarvis and was abandoned under the advisement of ICT. Email platform integration should form part of marketing automation recommendations. Do not believe there should be a focus on integrating swift in Q4.

    What Jess see value in is exploration of Blackthorn events as integrated TAP events option - currently using swift event desk or swoogo


    @jessica.wood - I updated with your feedback (See above)

     

     

    AQ releases (4 version upgrade to AQ 25)

    Part 1

     

     

     

     

     

    Q4

    Y

    complete

     

    Charter of Accounts

     

    Large

     

     

     

    revisit

     

     

     

    Opportunities Evaluation
    may lead to reviewing -Opportunity to Gift (phase 2)

     

     

     

     

    Laila

    Opportunity to gift future work

    Requires status update from @laila.valterio

     

    Requires status update from @laila.valterio

     

     

    AQ Gift Processing Issues

     

    Medium

     

     

     

    AQ consultation/ training

    AQ to check backlog of zendesk tickets

    Y

    Waiting for signatures

     

    AQ demo to Program Director (detailed)

     

    small

     

     

    Rommel

    Q4

    Y

     

     

    SF Winter Release 24

     

    Medium

     

     

     

    Q4 - led by platform team

    Y

    In progress

     

    Anonymisation UAT

    CLOSE

    Large

     

     

    Monica,Yeng

    q4 - led by platform team

    Y

    Complete

     

    Roles and Permission  - User access requests in Salesforce.

    Currently 150 different permission sets to streamline (large - 5-6 sprints)

     

    Extra Large

     

    Currently 150 different permission sets to streamline

     

    [TAPSS-144] Profiles/Permissions/Roles review and enhancements post-Wellbeing merge - JIRA (atlassian.net)

    Yeng
    Polina
    Pat/ Banila

    Preventing ServiceNow form to be functional.

    ServiceNow Product Team (ICT)

    High priority-

    Bringing in Yeng

    Y

     

     

    ASOP - Technical knowledge transfer when transitioning to post- go live support model

     

    Medium

     

    [TAPSS-1636] Technical knowledge transfer from ASOP - JIRA (atlassian.net)

     

     

    Y

     

     

    Multiple GIN error - investigation

     

    needs impact assessment feedback

     

     

     

    Will start in Hogwarts as a requirement to understand

    What is the identifier that is universal for all systems starting in Jarvis--> GMR.---> reporting--> trust office

    Do we need sub identifiers , marking it up to the gift itself

    Y

    In progress

     

    Any work that impacts TAP product line because of Wellbeing moving out of salesforce - e.g. data deletion, turning off API, removing their custom fields, removing their custom workflow code 

     

     

     

     

    shut down wellbeing access and case data
    Remain dormant
    Api has flagged with Claes

     

    Need to confirm what we’ll do with the student integration.

     

    Not in Q4

    Platform team to own on their board

    N

     

     

    AQ release 25 (medium 3 sprints - mainly because of Smart batch requirements)

     

    medium

     

    Business will wait and ask for AQ advice

     

     

     

     

     

    End of year processing support - crucial period for closing donations and pledge for Campaign Target for  TAP (Medium : 3-4 sprints)

     

    medium

     

    [TAPSS-1635] End of year processing support - critical support - JIRA (atlassian.net)

     

     

    Y

     

     

    Technical knowledge transfer from Hogwarts?

     

    medium

     

    [TAPSS-1634] Technical knowledge transfer from Hogwarts - JIRA (atlassian.net)

     

     

    Y

     

     

    Planned giving?

     

    Requires impact assessment feedback from @laila.valterio and @AlainGasquet

     

    Laila will further consult with Harpreet
    Alain will check with Harpreet on a work around.

    Harpreet/ Laila/ Alain

     

    Requires feedback from Laila and Alain before allocating resourcing

     

     

    BAU buffer- contingency planning

     

    Small

     

     

     

     

    Y

     

     