Attention: Confluence is not suitable for the storage of highly confidential data. Please ensure that any data classified as Highly Protected is stored using a more secure platform.
If you have any questions, please refer to the University's data classification guide or contact ict.askcyber@sydney.edu.au

Skip to end of banner
Go to start of banner

2020-10-16 Stand-up notes

Skip to end of metadata
Go to start of metadata

You are viewing an old version of this content. View the current version.

Compare with Current View Version History

« Previous Version 10 Next »

Date

Participants

Standing Agenda

  • Progress against plan

  • Outstanding actions

  • Blockers

  • Focus for next week

  • Focus for following week

  • General

Discussion

Progress against plan

Data testing - Another load earlier today to fix defects. Mostly small errors. Aim to refresh UAT next Wednesday. Accounts and Contact counts. Need to consider how to prepare this is part of cutover and also what QA is AQ doing. Jules Levin to add to cutover plan. Coders to review and Griffin does QA and check tickets before handing over.

Through cutover, Finance and TAP need to know totals and be able to extract emails for EDMs.

Griffin - GA meeting spent too much time on what works. Need to focus on what doesnt work. Griiffin says to work through rather than talk about it.

Outstanding Actions

See above

Blockers

Focus for next week

  1. Finish Sprint 3

  2. Data conversion testing

Focus for following week

  1. Commence Sprint 4.

  2. UAT data refresh

Action items

  • Jules Levinto add AQ data conversion QA to cutover plan

Outstanding Actions

Decisions