2020-10-07 Stand-up notes

Skip to end of metadata
Go to start of metadata

You are viewing an old version of this content. View the current version.

Compare with Current View Version History

« Previous Version 7 Next »

Date

Participants

Standing Agenda

  • Progress against plan

  • Outstanding actions

  • Blockers

  • Focus for next week

  • Focus for following week

  • General

Discussion

Progress against plan

Data - Voids and write offs not in. They were loaded, but pulled out and reviewing. Raised defects are being addressed with data loading. About half tickets ready for retesting. When ready for retest, Griffin updates tickets accordingly.

Two options being considered for cutover at end of year. One is to stop using Advance week before university end of year shutdown and second is to stop using Advance on 22 December. Stopping later will result in final cutover to AQ being completed mid January. Lori Stirling (Deactivated) to advise if AQ has any comments on later option, the details of which were advised in email from Jules.

Documentation and Training material - Griffin advised that hand over documentation is usually in the form of AQ Zen desk documentation which is provided at go-live. Further discussion with Lori on as-built documentation and training material for Gift Processing.

Api raised concern with data still not fully loaded. E2E gift processing parallel testing required before final cutover

Jules Levin concerns with data loading with Lori Stirling (Deactivated) and arrange meeting to discuss data, documentation and cutover.

Outstanding Actions

See above

Blockers

Gift data load

Focus for next week

  1. Continue Sprint 3

  2. Data conversion testing

Focus for following week

  1. Complete Sprint 3.

  2. Sprint 4 planning

  3. UAT data refresh

Action items

Outstanding Actions

Decisions