Date
Participants
Lori Stirling (Deactivated)(apologies)
Standing Agenda
Progress against plan
Outstanding actions
Blockers
Focus for next week
Focus for following week
General
Discussion
Progress against plan
Data - Griffin Update > programmer loading. Some defects are misunderstanding. Some are voids. Griffin still to look at what Rachel send through yesterday. AQ not designed to include a source field but rather campaigns. CYA. Client paid to put in so there now. Advance has 9 locations where source comes from. Lori says not a lot of clients use it. Sources not mapped.
USYD concerned that only 7 weeks to cutover and there are still data conversion defects. Griffin Homan (Deactivated) to continue processing, USYD will have an internal meeting with the testers to confirm status. At Friday, standup review status and assess what mitigation strategy is required and point at which defects need to be resolved in order not to impact cutover.
Outstanding Actions
See above
Blockers
Refinement data conversion
Focus for next week
Continue Sprint 4
Data conversion testing
Focus for following week
Complete Sprint 4.
UAT data refresh
Action items
- Brad Fernandes (Unlicensed) to document in user stories required required to be on AQ roadmap that cannot be implemented in MVP. Also send list in email to Lori and Griffin
Outstanding Actions