2020-10-21 Stand-up notes

Skip to end of metadata
Go to start of metadata

You are viewing an old version of this content. View the current version.

Compare with Current View Version History

« Previous Version 11 Next »

Date

Participants

Standing Agenda

  • Progress against plan

  • Outstanding actions

  • Blockers

  • Focus for next week

  • Focus for following week

  • General

Discussion

Progress against plan

Data - Griffin been talking to the programmers. Making good progress. Majority of issues are missing records that fall out because of logic. Going through the ones assigned to Griffin. Need to talk to Lori about created and modified dates. Aim to complete by end of the week, except data counts. Single list. Need to make a call on when to refresh the sandbox.

Smart batch and flexibility with pledges. Confidence comes from parallel testing. Changes are on AQ roadmap. Want to know what is on roadmap for requirements that cannot be done for MVP. Brad Fernandes (Unlicensed) / john.humphreys to flag with AQ what needs to be on roadmap, Prepare user stories for these. Also send a email stating what functionality is required for roadmap. Include why it needs. How are these tracked in AQ land? Once go-live and access to zendesk and formally submit with tracking.

Things that are out of scope for MVP but required immediate post-go - Brad Fernandes (Unlicensed) to add a sprint for post-go live.

Api concerned about post go-live. Is that something we can do before go-live? Griffin say should prioriise and time. Data changes cant be done until go-live

Campaigns hierarchy - Jules Levin to raise with Lori Stirling (Deactivated) about whether this can be done as part of data conversion as still ongoing.

Outstanding Actions

See above

Blockers

Focus for next week

  1. Continue Sprint 4

  2. Data conversion testing

Focus for following week

  1. Comlpete Sprint 4.

  2. UAT data refresh

Action items

Outstanding Actions

Decisions