Date
Participants
Standing Agenda
Progress against plan
Outstanding actions
Blockers
Focus for next week
Focus for following week
General
Discussion
Progress against plan
Data conversion - All data has been loaded including reversal table, AQ working through fixing defects raised from testing.
Cut over from Advance to AQ - Lori advised that AQ Management are concerned that if started at the end of December, the cutover will extend well into January and SOW period is to end of December 2020.
If going to run Advance to end of year shutdown, AQ all processing to complete by midday on 22 December and spatial data removed and Advance data dump provided thereafter. On 28/29 December, USYD will need to sign off on Account, Contact and counts. Someone from DB team will need to be on standby through shutdown period in case of issues. Jules Levin to schedule a workshop to work through the cutover plan
Outstanding Actions
See above
Blockers
Focus for next week
Continue Sprint 3
Data conversion testing
Focus for following week
Complete Sprint 3.
Sprint 4 planning
UAT data refresh
Action items
- Jules Levin to schedule cutover workshop
Outstanding Actions