Date
Participants
Standing Agenda
Progress against plan
Outstanding actions
Blockers
Focus for next week
Focus for following week
General
Discussion
Progress against plan
Data - All raised defects but one have been fixed. Griffin Homan (Deactivated) to confirm and update tickets. Mods for gifts and running one update on the outstanding bio items. Opportunities are in. Reversal tables are a problem. In first conversion they were not brought in. @jules to confirm if USYD requires the reversal tables.Should an additional conversion be introduced prior to the final one to mitigate the risk of experiences significant issues with final conversion. Lori Stirling (Deactivated) advised that at this stage she doesn't believe it is warranted.
Discussed need to for AQ to work through Gift Admin processes using outcomes of the GA processes. Jules Levin to provide list of the scenarios to AQ.
Cutover option - Process transactions in Advance to 22 December and complete cutover by mid January. Lori advised that on 29 December, Accounts and Contacts numbers would needed to be validated by USYD prior to full data load. USYD will need to have people available from 4 January for data conversion testing.
Need to be able to process recurring pledge payments on 11 Jan. Monica proposed a workaround for this which needs to be tabled with AQ to assess if any issues
Lori Stirling (Deactivated) to confirm AQ resource availability in Dec/Jan
Outstanding Actions
See above
Blockers
Gift data load
Focus for next week
Continue Sprint 3
Data conversion testing
Focus for following week
Complete Sprint 3.
Sprint 4 planning
UAT data refresh
Action items
- Lori Stirling (Deactivated) to send through weekly T&M SOW timesheets.
- Jules Levinto confirm if USYD requires the reversal tables
- Lori Stirling (Deactivated) to confirm AQ resource availability in Dec/Jan
- Jules Levin to provide list of the GA scenarios to AQ that need to be worked through
Outstanding Actions