Standing Agenda

  • Progress against plan

  • Outstanding actions

  • Blockers

  • Focus for next week

  • Focus for following week

  • General

Discussion

Progress against plan

Data conversion - Lori and Griffin update - - Fixes rolling In constantly. List is shrinking. Fixing a ton of count issues. Down to negligible numbers. Excluding contacts marked for delete.

Campaign table loaded and mapped. Campaigns should be going in shortly and will then update with parent child relationship. Do a full review of all data tickets. Campaigns are about half way in. Aiming for tomorrow Sydney time to complete.

Leads object - Will need to setup the correct security on the objects. Which is gift admin.reviewing defects list. Griffin and Lauren going through open items. Griffin says between 10 and 20 outstanding issues. 5 Gift related and rest are bio related. About 20 ticket relate to last modify and update dates. Will tackle last. About 10 outstanding related to opportunities. Once that sorted will go away. More Jira tickets than issues. Jules Levin to setup up a test review. Can test be re-assigned. Fix the outstanding ones by Friday our time. Have someone to walk through from yeng team and CSMs..

To mitigate prolonged final data conversion, Lori Stirling (Deactivated) advised that her and Griffin will go though test cases for the list of defects during the Xmas break. prior to USYD commencing data conversion testing on 4 January.

Target Friday to close out defects. UAT commences on 23 November. Dependency for UAT is to refresh the UAT sandbox with PROD data.

Assess on Friday about refresh UAT.

How can PD do mass modify opportunity and account assignments - Load new release in December. Lori offer they would do it over the break if USYD wants to introduce the new release

Outstanding Actions

See above

Blockers

Refinement data conversion

Focus for next week

  1. Continue Sprint 45

  2. Data conversion testing

Focus for following week

  1. Complete Sprint 45.

  2. UAT data refresh

Action items

Outstanding Actions

Decisions