Priority planning for TAP Product Line (Solution Slayers) for work commencing ___ October.
Key Stakeholders:
Api, Laila Valterio, Alain Gasquet, Jessica Wood, Monica Kluegel, , Miranda Adams
People to inform:
Tina Verna, Demelza Birtchnell… (Please add people here)
GA team time dependencies:
Internal Audit - present to end of October
AQ consult - aiming 2 October
GA/ GI - assessment - Oct to November
End of year processing - mid November - Dec
Rank | EPIC | Sizing | Duration estimation (minimum) | Business requirements | Business SME required | Impact/Dependencies | To be included in Q4 | Status | |
---|---|---|---|---|---|---|---|---|---|
Sydney Student - fix mulesoft integration | TAPSS-318 | Large (5 to 6 sprints) | 2.5 month | Assessment + Build | 16 stories completed | ||||
Integration fix - iModules | TAPSS-1160 | Beha | Vendor management - -raise | Needs further assessment | Requires confirmation | ||||
Swift and swoogo | Extra Large | Feedback from SME (Jess): | Jess and Polina | Check Luke demo |
| ||||
|
|
|
| ||||||
Charter of Accounts | Large | revisit | |||||||
Opportunities Evaluation | Laila | Opportunity to gift future work | Requires status update from laila.valterio | Requires status update from laila.valterio | |||||
AQ Gift Processing Issues | Medium | AQ consultation/ training | Y | Waiting for signatures | |||||
AQ demo to Program Director (detailed) | small | Rommel | Q4 | Y | |||||
SF Winter Release 24 | Medium | Q4 - led by platform team | Y | In progress | |||||
|
| Large |
|
|
| In progress | |||
Roles and Permission - User access requests in Salesforce. | Extra Large | Currently 150 different permission sets to streamline | Yeng | Preventing ServiceNow form to be functional. | Y | ||||
ASOP - Technical knowledge transfer when transitioning to post- go live support model | Medium | [TAPSS-1636] Technical knowledge transfer from ASOP - JIRA (atlassian.net) | Y | ||||||
Multiple GIN error - investigation | needs impact assessment feedback | Will start in Hogwarts as a requirement to understand | Y | In progress | |||||
Any work that impacts TAP product line because of Wellbeing moving out of salesforce - e.g. data deletion, turning off API, removing their custom fields, removing their custom workflow code | shut down wellbeing access and case data Need to confirm what we’ll do with the student integration. | Not in Q4 | N | ||||||
AQ release 25 (medium 3 sprints - mainly because of Smart batch requirements) | medium | Business will wait and ask for AQ advice | |||||||
End of year processing support - crucial period for closing donations and pledge for Campaign Target for TAP (Medium : 3-4 sprints) | medium | [TAPSS-1635] End of year processing support - critical support - JIRA (atlassian.net) | Y | ||||||
Technical knowledge transfer from Hogwarts? | medium | [TAPSS-1634] Technical knowledge transfer from Hogwarts - JIRA (atlassian.net) | Y | ||||||
Planned giving? | Requires impact assessment feedback from laila.valterio and AlainGasquet | Laila will further consult with Harpreet | Harpreet/ Laila/ Alain | Requires feedback from Laila and Alain before allocating resourcing | |||||
BAU buffer- contingency planning | Y |
...
Small | Y |