Page Properties

Background

Sprint 17 achievement are listed as -

  • Cyber Security Penetration testing completed

  • Stata and MiniTab licenses procured and Predictive modelling commenced

  • Aperture DS training commenced.

  • Updates to the Pledge reminder notice

  • Enhancements to Peoplesoft files

  • Gift in Will stage

  • Updates to Opportunity - Ask amount,

  • Community Giving Dashboards

  • Funds raised by Alumni

  • Optimise the flows for Gift processing - Raised with Salesforce

  • Gift club memberships

  • Data conversions fixes to Addresses (suburbs)

  • Receipts to be on-hold -

  • Annual receipts

  • Event registration

  • Updates to CG dashboards

Statistics at the end of Sprint

...

Retrospective

Conducted using IdeaBoardz to collaborate and gather feedback. Participants were given an opportunity to vote on the feedback for discussion.

What went well?

Point

Votes

longer sprint period

5

clear on stories to focus on (i.e. PowerPoint @ Standups)

2

anshu completed first phase of speadsheet upload to batch items

1

Balancing with BAU to address users' feedback / needs

0

3 weeks sprint!

0

Have breathing space to deal with BAU and Sprint works

0

We still like each other!

7

Good team communication and collaboration

3

clear goals in place

2

Technology Roadmap provides a framework of priorities for 6 months

2

Big ticket items being completed

0

In office face to face discussions about different tasks help a lot in navigating it to completion.

0

3 week sprint is a good idea

0

What can be improved?

Point

Votes

Stand-up meetings - Focus 1 activity for the day and ask team for help.

1

Standups could be less frequent if working on larger ticket items

1

Advise team of any planned leave

1

can I suggest we reduce the standups to twice weekly and make them longer, allowing time to discuss issues with the groupbetter understand what resources are available for planning

1

Focus on blocks of stories / functions to consolidate adding value per sprint (no spreading across too many elemenets)

0

Mapping dependencies / stress period for external stakeholders (e.g. ASR with appeals, EOY, etc.)

0

ensure must have items are allocated to a developer at the start of the sprint so we know what we can deliver

0

Action Items

Point

Votes

communicate all progress to stakeholders [e.g. Sprint achievements]

0Drinks

3

 

...

Image Added