Date

04

Participants

Standing Agenda

  • Progress against plan

  • Outstanding actions

  • Blockers

  • Focus for next week

  • Focus for following week

  • General

Discussion

Progress against plan

Data - Griffin Update > programmer loading. Some defects are misunderstanding. Some are voids. Griffin still to look at what Rachel send through yesterday. AQ not designed to include a source field but rather campaigns. CYA. Client paid to put in so there now. Advance has 9 locations where source comes from. Lori says not a lot of clients use it. Sources not mapped. USYD concerned that only 7 weeks to cutover and there are still data conversion defects. Griffin Homan (Deactivated) to continue processing, USYD will have an internal meeting with the testers to confirm status. At Friday, standup review status and assess what mitigation strategy is required and point at which defects need to be resolved in order not to impact cutover. update - A lot accounts figured. Will need to let Yeng know finished off counts for base objects which should make the other numbers align. Programmer working with Meredith on fixing gift pieces and will make one upload for gifts. Griffin can see lots of tickets being closed. Most assigned pieces have been reassigned. One issue is don't have opportunities in as were dropped for fixed. There are 2 ticket related to opportunities. Changes rolled out a few days ago have been closed. Lori, Programmers went through gift defects and will get NB ones done. Lower priority will come later. Gift will be done by end of USA week so expect good data by Monday. Opportunities should be done shortly. Counts will be another few days as will be back and forth.

Where is Community Portal on the AQ roadmap - Griffin Homan (Deactivated) to check if AQ has a estimate.

To get items onto roadmap AQ roadmap, send email to Lori and Griffin. Will be able to submit directly through zendesk when access is provided in a few weeks.

Griffin advised that for Opportunity Teams access to Opportunities can only be restricted by Permission sets. Post MVP sharing rules can be added

Outstanding Actions

See above

Blockers

Refinement data conversion

Focus for next week

  1. Continue Sprint 45

  2. Data conversion testing

Focus for following week

  1. Complete Sprint 45.

  2. UAT data refresh

Action items

  •  Brad Fernandes (Unlicensed) to document in user stories required required to be on AQ roadmap that cannot be implemented in MVP. Also send list in email to Lori and Griffin

Outstanding Actions

Decisions