Standing Agenda

  • Progress against plan

  • Outstanding actions

  • Blockers

  • Focus for next week

  • Focus for following week

  • General

Discussion

Progress against plan

Data load - Updating some bio data, addresses being worked on - Stuck on two things - Apex issue with Gifts. Escalated to a senior programmer. Also Relationships; Risk mitigation plan required for final data conversion. USYD people will be on end of year break from 22 December and not available for Advance datapumps or data testing.

Defects have been raised on data that has been tested. Griffin Homan (Deactivated) to advise when Gift data Three defects raised.

No need for Lori t attend this week’s Steerco meeting

Receipting function - not ready for release Lori Stirling (Deactivated) to confirm if a point release will be out this week.

Reports and dashboards - Lori advised that https://reportforce.blog/ is a useful reporting resource. Lori advised that role hierarchy is not part of AQ scope and their customers do not typically use it

Griffin confirmed that bluesky configs have been pushed to UAT and PRD

Lori advised that estimate for Degrees object is 5-7 hours and it has already been coded advised that no significant issues. Assumption is the fixes can be done by upserting rather than another conversion. Some user stories assigned to sprint 2 could be blocked due to data defects as UAT has data from first conversion. {post meeting note: Griffin Homan (Deactivated) to review the user stories and note which are blocked for config or testing}.

Once all data is loaded, tested completed and defects fixed, UAT sandbox with be refreshed with PRD data.

Monica Kluegel has documented Gift outcomes for the project. These will be shared with AQ to talk through how to achieve the outcomes. May need several Gift processing walkthroughs.

Receipting Function - Was pushed into the org on Saturday. Some issues identified which are being fixed. Apsona report building component has not yet been completed. Workshop scheduled for tomorrow on the Receipting Function will go ahead as planned.

Document Storage - Not part of AQ MVI/MVP. Lori says too big a scope to include in Trevor’s workload. USYD to consult with Trevor for advise.

Outstanding Actions

See above

Blockers

Gift data load

Focus for next week

  1. Backlog Refinement.

  2. Complete config sprint 1

  3. Commence Config Continue with Config and Integration sprint 2

  4. Data conversion testing

Focus for following week

  1. Complete Sprint 2.

  2. Backlog refinementCommence Sprint 3