Date
11
Participants
Lori Stirling (Deactivated) (apologies)
Standing Agenda
Progress against plan
Outstanding actions
Blockers
Focus for next week
Focus for following week
General
Discussion
Progress against plan
Class codes - Updated mapping sent by Griffin. Programmers will get in shortly. So should be part of the AQ data load.
Household scripts issue - Where one Contact had been removed by request, they were put into a separate Account. A lot of the accounts where removed by request and one not so put on separate accounts. Programmer working on this and shakedown test issues found by Griffin. Griffin expect all data except Gifts to be available Monday morning Sydney time for testing.
Target for completion of testing is 23 September. This will allow UAT to be refreshed with PRD data for the second sprint.
Area of Study object (Degrees) - Lori Stirling (Deactivated) to provide estimate of how much of the variation work order will be consumed.
Subscriptions and Dues Object - Monica and Rachel should be able to start using. Griffin Homan (Deactivated) to confirm permission set has been setup
Special handling preferences - Migrated to campaigns. USYD preference is to be on Contacts. Griffin said can be done on Contact by utilising a multi pick list. Cant be done for MVP as coded to campaigns. Griffin Homan (Deactivated) to demonstrate how to do this. Jules Levin to note for AQ to cover in campaigns and add to backlog to move to contacts post MVPData load - Updating some bio data, addresses being worked on Griffin Homan (Deactivated) to advise when Gift data Three defects raised.
No need for Lori t attend this week’s Steerco meeting
Receipting function - not ready for release Lori Stirling (Deactivated) to confirm if a point release will be out this week.
Reports and dashboards - Lori advised that https://reportforce.blog/ is a useful reporting resource. Lori advised that role hierarchy is not part of AQ scope and their customers do not typically use it
Griffin confirmed that bluesky configs have been pushed to UAT and PRD
Lori advised that estimate for Degrees object is 5-7 hours and it has already been coded
Outstanding Actions
See above
BlockersData load for refinement conversion testing
Focus for next week
Backlog Refinement.
Complete config sprint 1
Commence Config sprint 12
Data conversion testing
Focus for following week
Parallel use case testing.
Data conversion testing
Config sprint 1Sprint 2.
Backlog refinement
Action items
- Lori Stirling (Deactivated) to provide estimate of how much of the variation work order advise when Receipting function will be consumedreleased.
- Griffin Homan (Deactivated) to demonstrate how to move special handling preferences to contacts
- Jules Levin to note for AQ to cover in campaigns and add to backlog to move to contacts post MVP
Outstanding Actions