Priority planning for TAP Product Line (Solution Slayers) for work commencing ___ October.
Key Stakeholders:
Api, Laila Valterio, Alain Gasquet, Jessica Wood, Monica Klugel, , Miranda Adams
People to inform:
Tina Verna… (Please add people here)
Rank | EPIC | Sizing | Duration estimation (minimum) | Business requirements | Business SME required | Impact/Dependencies | To be included in Q4 | |
---|---|---|---|---|---|---|---|---|
Sydney Student - fix mulesoft integration | TAPSS-318 | Large (5 to 6 sprints) | 2.5 month | Assessment + Build | ||||
Integration fix - iModules | TAPSS-1160 | Beha | Vendor management - -raise | Needs further assessment | ||||
Swift and swoogo | Feedback from SME (Jess): | Jess and Polina | Check Luke demo | Y | ||||
AQ releases (4 version upgrade to AQ 25) | Q4 | Y | ||||||
Charter of Accounts | revisit | |||||||
Opportunities Evaluation | Laila | Opportunity to gift future work | ||||||
AQ Gift Processing Issues | AQ consultation/ training | Y | ||||||
AQ demo to Program Director (detailed) | Rommel | Q4 | Y | |||||
SF Winter Release 24 | Q4 - led by platform team | Y | ||||||
Anonymisation UAT | CLOSE | q4 - led by platform team | Y | |||||
Roles and Permission - User access requests in Salesforce | Currently 150 different permission sets to streamline | Preventing ServiceNow form to be functional. | ||||||
ASOP - Technical knowledge transfer when transitioning to post- go live support model | Q4 | Y | ||||||
Multiple GIN error - investigation | Will start in Hogwarts as a requirement to understand | |||||||
Any work that impacts TAP product line because of Wellbeing moving out of salesforce - e.g. data deletion, turning off API, removing their custom fields, removing their custom workflow code | shut down wellbeing access and case data | Not in Q4 | ||||||
AQ release 25 (medium 3 sprints - mainly because of Smart batch requirements) | Business will wait and ask for AQ advice | |||||||
End of year processing support - crucial period for closing donations and pledge for Campaign Target for TAP (Medium : 3-4 sprints) | Q4 | Y | ||||||
Roles and Permission - User access requests in Salesforce. Currently 150 different permission sets to streamline (large - 5-6 sprints) | Q4 | Y | ||||||
Technical knowledge transfer from online payments | ||||||||
Multiple GIN error - investigation | ||||||||
Technical knowledge transfer from Hogwarts? | Q4 | Y | ||||||
Planned giving? | Laila will further consult with Harpreet | Harpreet/ Laila/ Alain | Requires feedback from Laila and Alain before allocating resourcing | |||||
BAU buffer- contingency planning |
GA team time dependencies:
Internal Audit - present to end of October
AQ consult - aiming 2 October
GA/ GI - assessment - Oct to november
End of year processing - mid november - Dec