Background
The Sprint objectives covered the following -
Reporting
Opportunities
Gift Administration
Community Giving
Change Management
Statistics at the end of Sprint
Sprint 6 included Data Conversion bugs and UAT support that took precedence and priority over Sprint 6 User Stories. These numbers were not reflected in the Sprint 6 - Overall status. It has been added below for reference (Note: These are the overall stats at the end of the Sprint).
Cumulative Flow Diagram
CFD for Sprint 6 - User Stories
CFD for Data Conversion testing - Bugs
Retrospective
Conducted using IdeaBoardz to collaborate and gather feedback. Participants were given an opportunity to vote on the feedback for discussion.
What went well? | |
Point | Votes |
On-site team day with UAT Testers and Champions was a good day for collaboration. Lots of productive discussions with quick resolution time. | 3 |
UAT refresh went well thanks to all collaboration works from the team and with our senior tech AQ | 1 |
Team continues to work with high intensity to complete MVP user stories in time for go-live | 1 |
Good team collaboration and communication with AQ, ICT, Advancement services team | 1 |
UAT testers gained speed and asking great questions | 0 |
Core delivery team doing well to juggle between data conversion testing, Sprint 6 tickets and UAT test support | 0 |
The channel for testers to post questions/issues was a good idea and great collaboration from the team with everyone jumping to help answer and resolve issues | 0 |
What can be improved? | |
Point | Votes |
Data conversion testing and bug fixes consuming significant time, affecting configuration output | 2 |
We still have BAU data extract come through that will taken up our times | 0 |
Mention any object config changes in the standups so if we see any unusual errors we can try and identify the potential cause quickly | 0 |
For the next refresh go better we need to make sure all change objects are registered in deployment registered | 0 |
Action Items | |
Point | Votes |
@Jules - Organise a meeting to draft a plan for Production Data conversion testing. (e.g. Integrity scripts, testing scripts) | 0 |
Keep deployment registry updated | 0 |
Config changes should be mentioned in daily stand-up meetings | 0 |