Background

The Sprint objectives covered the following -

  • Reporting

  • Opportunities

  • Gift Administration

  • Community Giving

  • Change Management

Statistics at the end of Sprint

Image Modified

Sprint 6 included Data Conversion bugs and UAT support that took precedence and priority over Sprint 6 User Stories. These numbers were not reflected in the Sprint 6 - Overall status. It has been added below for reference (Note: These are the overall stats at the end of the Sprint).

Cumulative Flow Diagram

CFD for Sprint 6 - User Stories

CFD for Data Conversion testing - Bugs

Retrospective

Conducted using IdeaBoardz to collaborate and gather feedback. Participants were given an opportunity to vote on the feedback for discussion.

What went well?

Point

Votes

On-site team day with UAT Testers and Champions was a good day for collaboration. Lots of productive discussions with quick resolution time.

3

UAT refresh went well thanks to all collaboration works from the team and with our senior tech AQ

1

Team continues to work with high intensity to complete MVP user stories in time for go-live

1

Good team collaboration and communication with AQ, ICT, Advancement services team

1

UAT testers gained speed and asking great questions

0

Core delivery team doing well to juggle between data conversion testing, Sprint 6 tickets and UAT test support

0

The channel for testers to post questions/issues was a good idea and great collaboration from the team with everyone jumping to help answer and resolve issues

0

What can be improved?

Point

Votes

Data conversion testing and bug fixes consuming significant time, affecting configuration output

2

We still have BAU data extract come through that will taken up our times

0

Mention any object config changes in the standups so if we see any unusual errors we can try and identify the potential cause quickly

0

For the next refresh go better we need to make sure all change objects are registered in deployment registered

0

Action Items

Point

Votes

@Jules - Organise a meeting to draft a plan for Production Data conversion testing. (e.g. Integrity scripts, testing scripts)

0

Keep deployment registry updated

0

Config changes should be mentioned in daily stand-up meetings

0